Timeline

Date Action / Activity
1938 Existing City Hall constructed
April 2006 Downtown Sub Area Plan Process begins
July 2006 City Hall included in the 2007-2013 Capital Facilities plan adopted by City Council
January 2009 Bothell City Council chooses the existing location (18305 101st Avenue NE) as the location for its future City Hall following a three site massing study conducted by Rice Fergus
July 2009 Downtown Visioning Process completes, Subarea Plan finalized and accepted by City Council
July 2010 City issues Request for Qualifications (RFQ) for development partner
July 2010 City holds Pre-Submittal Conference: 150 consultants attend.
September 2010 Updated Capital Facilities Plan adopted by City Council anticipating the 2011 design of the City Hall/City Center
September 2010 City receives developer qualifications from 15 teams
October 2010 City issues Request for Proposal (RFP) to a shortlist of five development teams
December 2010 City receives proposals from 4 shortlisted development teams
January 2011 Selection committee interviews 4 shortlisted development teams
February 2011 Vulcan Real Estate selected as City's development partner for City Hall
March – May 2011 Community Workshops for City Hall
July 2011 Pre-construction activities on site
September 2011 Council decision on City Hall design and GMP (Guaranteed Maximum Price) construction cost.
December 2011 Outbuildings vacated