Timeline

The Downtown Revitalization Plan which includes multiple city initiatives that span several years was officially kicked-off in April 2010. Below is a timeline showcasing the estimated timing for projects currently planned. Click here for a more detailed description of each city initiative.

Crossroads Project Schedule:
Demolition: April 2010 - July 2010
Roadway: July 2010-October 2012

Wayne Curve Project Schedule:
May 2010 - December 2011

City Hall Project Schedule:
Design: 2010
Construction: 2011-2012
Estimated Completion: 2012

Multi-Way Boulevard Project Schedule:
Roadway: To occur with adjacent development as early as 2011

Main Street Project Schedule:
Concepts: 2010
Final Design: 2011
Construction (Enhancements): Begins 2013
Construction (Extension): To occur with adjacent development

Main Street Project Schedule:
Concepts: 2010
Final Design: 2011
Construction (Enhancements): Begins 2013
Construction (Extension): To occur with adjacent development

The Park at Bothell Landing:
Plan Adoption: May 2010
Construction: Begins 2012